Departments



Articles

Less

City Documents: Quasi-Judicial Petitions 2005
February 8th, 2005

City Documents: Quasi-Judical Hearing 2005-07
February 8th, 2005

City Documents: Quasi-Judicial Hearing 2005-08
February 8th, 2005

City Documents: City Commission Meeting Minutes February 1, 2005
February 6th, 2005

City Documents: Notice of City Election
February 6th, 2005

City Documents: Ordinance 378
February 3rd, 2005

City Documents: City Commission Agenda for February 1, 2005
January 28th, 2005

City Documents: CRA Minutes January 18, 2005
January 24th, 2005

City Documents: City Commission Meeting Minutes January 18, 2005
January 24th, 2005

City Documents: Historical Preservation/Architectural Review Board Meeting Minutes January 14, 2005
January 18th, 2005

City Documents: LPA Meeting Schedule for February 2005
January 14th, 2005

City Documents: City Commission Agenda for January 18, 2005
January 14th, 2005

City Documents: City Commission Meeting Minutes of January 4, 2005
January 7th, 2005

City Documents: Local Planning Agency Meetings
January 7th, 2005

City Documents: City of Cedar Key Agenda
December 31st, 2004

More

Water System and Streets Work Continues

Water System and Streets Work Continues

City Documents

During the week of January 3rd water main and water services replacement will be completed on Whiddon Avenue. Between January 4th and 5th work will begin on Second Street between "D" and "F" Streets.

The Contractor will be notifying customers on Second Street between "D" & "F" Streets that they will have an interruption in their water service at some point between January 5th and January 14th.

Using a trenchless technology called pipe bursting the contractor will pull the new 8" water main thru the existing 6" pipe. The existing smaller diameter pipe will be burst in place with a cone shaped cutting tool with the new 8" pipe pulled behind it. Some advantages of this method include faster construction times and minimizing the need for open trenches.


The new water main is pre-chlorinated and tested prior to installation allowing the system to be put into service the same day it is installed. The new water main will increase the gallons per minute flow, quality of the water and provide addition fire protection. Additionally, new fire hydrants will be installed in areas that did not have adequate protection.

Water main replacement and streets reconstruction will not occur on the balance of Second Street (between "D" and Depot Streets) until after the Spring Arts Festival in April.

Street reconstruction and resurfacing work will continue thru January in the downtown residential areas. Some streets will have temporary closures and or detours, please drive carefully.