Departments



Articles

Less

News: Commission Approves RV Park Owner`s Request for Exemption
April 5th, 2008

News: Boring Issue Debated at Length
April 5th, 2008

News: "Earth Hour" Tonight at 8 p.m.
March 29th, 2008

News: Music Comes to CK School
March 27th, 2008

News: Three Contests in Cedar Key`s May 6 Election
March 24th, 2008

News: Chamber to Sponsor Two New Festivals
March 22nd, 2008

News: Correction: June Show
March 22nd, 2008

News: Marina Problems Debated
March 21st, 2008

News: New "Clam Cop" Assigned to Area
March 21st, 2008

News: Special Pies at Special Auction
March 20th, 2008

News: Water Pipeline to Airport Area
March 19th, 2008

News: Big Dock Construction Progress
March 13th, 2008

News: LPA Asks to be Dissolved
March 7th, 2008

News: Shell Mound Fishing Pier
March 3rd, 2008

News: Wildlife Refuge Open House
February 24th, 2008

More

Delayed Dock Repair Drags On

Delayed Dock Repair Drags On

Jim Hoy


One may ask, "Why still closed?"

The Levy County Engineer condemned the "Big Dock," Cedar Key's biggest and perhaps primary tourist attraction on September 30, 2004. Twelve days later Levy County applied for FEMA funds to repair the storm damaged dock. Now, two years later, plans to rebuild the dock have not been completed. Bidding and construction are still months away.

One newspaper reported optimistically that the dock might reopen by Labor Day, 2005. Levy County officials now say that structural engineering plans may be finalized by "the first of November." Assuming bids go out in November, with thirty days for responses, construction might start in December, 2006. Current estimates are that construction could be completed in three months, possibly as early as April 1, 2007. That is with the hope that a competent large firm would get the contract.


Notice of dock closure regularly ignored.

Business owners on Dock Street say that closure of the dock for two years has hurt them in the pocketbook. Meanwhile, unauthorized use of the dock by spongers' boats continues. Recently two local artists bypassed a four foot barrier for a day of painting on the dock.