Departments



Articles

Less

News: Davis to Continue As Administrator
August 20th, 2008

News: CRA Director Gorman Fired, Greg Lang Interim Director
August 12th, 2008

News: Fire-Rescue Boat Approved by CRA
August 7th, 2008

News: The Big Dock Is Finished!
August 7th, 2008

News: Visitors Win Cedar Key News Contest
August 7th, 2008

News: Police Chief Search Progresses
August 4th, 2008

News: Management Change at Cedar Key Scrub
July 31st, 2008

News: Upper Limit Set on City Budget for 2008-2009
July 28th, 2008

News: Paving Plans Progress
July 16th, 2008

News: Big Dock (Unofficially) Opens
July 5th, 2008

News: Clams! Clams! Clams!
July 5th, 2008

News: CLAMERICA: Clamania Events
July 1st, 2008

News: CFCC to Expand in Levy County
June 28th, 2008

News: The Big, Big Dock
June 28th, 2008

News: Aquaculture Assn. Plans Meeting, Barbecue and Candidates` Forum
June 13th, 2008

More

Big Dock Funding Appeal

Big Dock Funding Appeal

Jim Hoy

Levy County officials have appealed to the Federal Emergency Management Agency (FEMA) for funding to repair the County's "Big Dock" in Cedar Key. A letter went to FEMA July 17 requesting addition to the $1,300,000 granted in 2005 because the current bid is $4,650,000 to reconstruct the dock. The dock was declared unsafe in 2004 following a hurricane.

Matt Weldon of the Levy County Parks Department told Cedar Key News that the bidding construction company is attempting to "value engineer" the project to reduce costs. The high costs come from concrete vs. wood construction, widened finger piers and larger sanitary facilities. Further complicating the project is the weakness of the bridge on the approach to the dock which prevents efficient concrete delivery.

Weldon said that the County hopes to get a reply from FEMA within thirty days. He added that a FEMA representative sees no problem with the project.

Click for printer friendly version