Departments



Articles

Less

News: Are You Sitting Down?
October 8th, 2009

News: CRA Supports School Art Program
October 7th, 2009

News: Cra Budget Approved
October 7th, 2009

News: Pipeline Gold & Pawn Opens
October 3rd, 2009

News: City Budget Finalized
October 2nd, 2009

News: Dangerous Dog Debate Deferred
September 21st, 2009

News: City Acts to Conserve Water at Park and Community Center
September 18th, 2009

News: Cell Tower Erection Problems
September 17th, 2009

News: Seasonal Flu Shots vs Swine Flu Shots
September 16th, 2009

News: CRA Budget Near Final
September 4th, 2009

News: New Water Board Member
August 27th, 2009

News: Lightning Strike Calls CK Volunteers Out
August 26th, 2009

News: Dog Not Danger on 3-2 Vote
August 20th, 2009

News: Music Lovers Hold Peaceful Protest at UF
August 20th, 2009

News: Budget Workshop: Cuts and Compromises
August 18th, 2009

More

Big Dock Reconstruction Begins / Updated Nov. 14

Big Dock Reconstruction Begins / Updated Nov. 14

Jim Hoy


The barge that will be used during the reconstructionof the Cedar Key dock.

The dramatic arrival of two tug boats and an eighty-five foot barge at the Cedar Key "Big Dock" on November 12 announced the start of rebuilding the storm-damaged dock. According to Levy County Coordinator Fred Moody, a contract for the construction project was to be signed November 13. After years and months of delay, a commitment by Levy County to provide $643,000 in supplementary funds in addition to $3.1 million in Federal Emergency Management Agency funds got the project underway. Mr. Moody told Cedar Key News that there is a possibility that FEMA will reimburse the County with cost over-run funds at the end of the project.

Update: On November 14 Lucas Marine Construction hosted an informational meeting regarding the reconstruction of the Cedar Key "Big Dock." Actual construction will begin on November 19, with a contract to finish work within 240 days. If that dadline is met the new dock will be finished before onset of the 2008 hurricane season.

Frank Subjinski, a Lucas Marine Vice President, said that the dock will have a concrete pre-stressed deck with a concrete overlay. There will be a thirty foot long aluminum ramp from Dock Street to the higher level dock. The ramp will be removable prior to a storm. Shafts for the concrete pilings will be drilled, an alternative to use of a pile driver.

The contract is for $3,596,357.