Departments



Articles

Less

News: Eagles Hawaiian Luau a Lulu
July 28th, 2007

News: Big Dock Funding Appeal
July 18th, 2007

News: CRA Pursues Second Street Property
July 18th, 2007

News: Emergency Management Plan Approved
July 18th, 2007

News: Police Beat: June 26 throught July 6
July 17th, 2007

News: Bid of $4,650,000 to Fix Big Dock
July 3rd, 2007

News: CRA to Fund Art Teacher
June 28th, 2007

News: Sinking Dock Street
June 21st, 2007

News: Police Report
June 20th, 2007

News: Big Dock Plans Go Forward
June 20th, 2007

News: And the Contest Winners Are...
June 19th, 2007

News: Park Plans Debated Again
June 13th, 2007

News: Hussan Proposes Revision of Commission Agenda Format
June 13th, 2007

News: City Commission Acts on Four Ordinances
June 13th, 2007

News: Water Treatment Plant Open House
June 10th, 2007

More

Big Dock Reconstruction Begins / Updated Nov. 14

Big Dock Reconstruction Begins / Updated Nov. 14

Jim Hoy


The barge that will be used during the reconstructionof the Cedar Key dock.

The dramatic arrival of two tug boats and an eighty-five foot barge at the Cedar Key "Big Dock" on November 12 announced the start of rebuilding the storm-damaged dock. According to Levy County Coordinator Fred Moody, a contract for the construction project was to be signed November 13. After years and months of delay, a commitment by Levy County to provide $643,000 in supplementary funds in addition to $3.1 million in Federal Emergency Management Agency funds got the project underway. Mr. Moody told Cedar Key News that there is a possibility that FEMA will reimburse the County with cost over-run funds at the end of the project.

Update: On November 14 Lucas Marine Construction hosted an informational meeting regarding the reconstruction of the Cedar Key "Big Dock." Actual construction will begin on November 19, with a contract to finish work within 240 days. If that dadline is met the new dock will be finished before onset of the 2008 hurricane season.

Frank Subjinski, a Lucas Marine Vice President, said that the dock will have a concrete pre-stressed deck with a concrete overlay. There will be a thirty foot long aluminum ramp from Dock Street to the higher level dock. The ramp will be removable prior to a storm. Shafts for the concrete pilings will be drilled, an alternative to use of a pile driver.

The contract is for $3,596,357.

Click for printer friendly version