Departments



Articles

Less

News: Commission Approves RV Park Owner`s Request for Exemption
April 5th, 2008

News: Boring Issue Debated at Length
April 5th, 2008

News: "Earth Hour" Tonight at 8 p.m.
March 29th, 2008

News: Music Comes to CK School
March 27th, 2008

News: Three Contests in Cedar Key`s May 6 Election
March 24th, 2008

News: Chamber to Sponsor Two New Festivals
March 22nd, 2008

News: Correction: June Show
March 22nd, 2008

News: Marina Problems Debated
March 21st, 2008

News: New "Clam Cop" Assigned to Area
March 21st, 2008

News: Special Pies at Special Auction
March 20th, 2008

News: Water Pipeline to Airport Area
March 19th, 2008

News: Big Dock Construction Progress
March 13th, 2008

News: LPA Asks to be Dissolved
March 7th, 2008

News: Shell Mound Fishing Pier
March 3rd, 2008

News: Wildlife Refuge Open House
February 24th, 2008

More

Big Dock Update February 5

Big Dock Update February 5

Jim Hoy


Pilings in place as of January 31, 2008.

Construction of Cedar Key's new Big Dock is moving forward, with 25 percent of the pilings completed according to Fran Subjinski of Lucas Marine Construction. Delivery of concrete for the pilings via Dock Street has worked well Subjinski said. However, soon the newer pilings will be set farther off-shore and concrete deliveries will come to the end of A Street to be shuttled by barge to the construction site. Once one third of the pilings are in place construction of the dock's deck will begin.

Soil conditions (depth of bedrock) have been found to be quite variable. That has made it necessary to put pilings much deeper than had been expected. The problem arose despite two geotechnical surveys by Universal Engineering in 2007. The first piling in place was thirteen feet deeper than expected, at 73 feet. The remainder of the pilings are expected to be set at 48 to about 60 feet deep according to Mr. Philip Chansey of Mills Engineering, the Levy County engineering firm overseeing the project.

The County's contract with Lucas Marine Construction allows for a two week delay in completion of the work. That agreement reset the completion date as July 28, 2008.