Departments



Articles

Less

News: G Street Storm Drain Project
October 13th, 2005

News: Refuge Staff Members Help in Relief Effort
October 12th, 2005

News: Flu Shots "Popular"
October 11th, 2005

News: Annexation Trial Balloon
October 5th, 2005

News: Water Treatment Test Underway
September 28th, 2005

News: Rains Brothers Acquitted of Poaching
September 27th, 2005

News: Local Humane Society Aids Katrina Animals
September 20th, 2005

News: City Prepares for Possible Lawsuit
September 16th, 2005

News: Decision on Downtown Project Delayed
September 16th, 2005

News: Commission Appoints Chief
September 7th, 2005

News: Dolphin Aids Rescue
September 7th, 2005

News: CRA Directorship Offer Accepted
September 1st, 2005

News: Chief Swogger to Leave Cedar Key
September 1st, 2005

News: Katrina in Cedar Key Update
August 30th, 2005

News: Music at the Dock Street Depot
August 30th, 2005

More

Bid of $4,650,000 to Fix Big Dock

Bid of $4,650,000 to Fix Big Dock

Jim Hoy

A single bid, one of $4,650,000, came in to Levy County for reconstruction of the Cedar Key "Big Dock." That bid is more than three times the $1,300,000 for dock reconstruction committed by the Federal Emergency Management Agency (FEMA) following the storm damage to the dock in 2004. Repeated delays for geotechnical studies and structural engineering plans have extended the reconstruction project.

Russell Engineering of Fort Lauderdale was the only bidder on the project, despite eight firms that were asked to submit bids. A representative of a firm that did not bid suggested that reengineering could reduce the project's cost.

Levy County officials have asked FEMA representatives to come to the dock site and reconsider FEMA's contribution the reconstruction effort. The FEMA team's visitation may come as early as the second week in July.

Click for printer friendly version