Departments



Articles

Less

News: Are You Sitting Down?
October 8th, 2009

News: CRA Supports School Art Program
October 7th, 2009

News: Cra Budget Approved
October 7th, 2009

News: Pipeline Gold & Pawn Opens
October 3rd, 2009

News: City Budget Finalized
October 2nd, 2009

News: Dangerous Dog Debate Deferred
September 21st, 2009

News: City Acts to Conserve Water at Park and Community Center
September 18th, 2009

News: Cell Tower Erection Problems
September 17th, 2009

News: Seasonal Flu Shots vs Swine Flu Shots
September 16th, 2009

News: CRA Budget Near Final
September 4th, 2009

News: New Water Board Member
August 27th, 2009

News: Lightning Strike Calls CK Volunteers Out
August 26th, 2009

News: Dog Not Danger on 3-2 Vote
August 20th, 2009

News: Music Lovers Hold Peaceful Protest at UF
August 20th, 2009

News: Budget Workshop: Cuts and Compromises
August 18th, 2009

More

Big Dock Update February 5

Big Dock Update February 5

Jim Hoy


Pilings in place as of January 31, 2008.

Construction of Cedar Key's new Big Dock is moving forward, with 25 percent of the pilings completed according to Fran Subjinski of Lucas Marine Construction. Delivery of concrete for the pilings via Dock Street has worked well Subjinski said. However, soon the newer pilings will be set farther off-shore and concrete deliveries will come to the end of A Street to be shuttled by barge to the construction site. Once one third of the pilings are in place construction of the dock's deck will begin.

Soil conditions (depth of bedrock) have been found to be quite variable. That has made it necessary to put pilings much deeper than had been expected. The problem arose despite two geotechnical surveys by Universal Engineering in 2007. The first piling in place was thirteen feet deeper than expected, at 73 feet. The remainder of the pilings are expected to be set at 48 to about 60 feet deep according to Mr. Philip Chansey of Mills Engineering, the Levy County engineering firm overseeing the project.

The County's contract with Lucas Marine Construction allows for a two week delay in completion of the work. That agreement reset the completion date as July 28, 2008.