Departments



Articles

Less

News: Sign Ordinance Revision Planned
December 16th, 2009

News: Garbage Contract Up for Bids?
December 16th, 2009

News: Whooping Cranes Half Way to Florida
December 7th, 2009

News: Former County Commissioners Convicted
December 5th, 2009

News: Duke Indicted on First Degree Murder
November 22nd, 2009

News: Grand Opening at Historical Society
November 16th, 2009

News: Book Launched in Cedar Key
November 15th, 2009

News: CRA Near Start of Major Project
November 13th, 2009

News: $2 Million Bond Set on Murder Suspect
November 6th, 2009

News: Update With Funeral Arrangements: Cedar Key Woman Dead, Husband In Custody
November 5th, 2009

News: Illegal Dumping Disrupts Sewage Treatment
November 5th, 2009

News: Commission Eyes Sign Ordinance, Solid Waste and Cell Tower
November 4th, 2009

News: FATAL BEAR FIGHT
October 23rd, 2009

News: Public Outcry Over Restaurant Name
October 21st, 2009

News: Seafood Festival Parade Winners
October 19th, 2009

More

Big Dock Update February 5

Big Dock Update February 5

Jim Hoy


Pilings in place as of January 31, 2008.

Construction of Cedar Key's new Big Dock is moving forward, with 25 percent of the pilings completed according to Fran Subjinski of Lucas Marine Construction. Delivery of concrete for the pilings via Dock Street has worked well Subjinski said. However, soon the newer pilings will be set farther off-shore and concrete deliveries will come to the end of A Street to be shuttled by barge to the construction site. Once one third of the pilings are in place construction of the dock's deck will begin.

Soil conditions (depth of bedrock) have been found to be quite variable. That has made it necessary to put pilings much deeper than had been expected. The problem arose despite two geotechnical surveys by Universal Engineering in 2007. The first piling in place was thirteen feet deeper than expected, at 73 feet. The remainder of the pilings are expected to be set at 48 to about 60 feet deep according to Mr. Philip Chansey of Mills Engineering, the Levy County engineering firm overseeing the project.

The County's contract with Lucas Marine Construction allows for a two week delay in completion of the work. That agreement reset the completion date as July 28, 2008.