Departments



Articles

Less

News: Brush Fire on Hodgson Avenue
June 12th, 2009

News: Water Board Accepts $1.3 Million CRA Project
June 9th, 2009

News: Dock Street Traffic Plan Approved
June 4th, 2009

News: Committee Planning Youth Activities
June 4th, 2009

News: Nuclear Plants Delayed Twenty Months
May 8th, 2009

News: Paddler on a Mission
May 5th, 2009

News: Solar Water Heater Saves $$$
May 4th, 2009

News: Seahorse Landing Receives Green Lodging Designation
May 1st, 2009

News: Cedar Key Fire Department Active in the First Quarter
April 26th, 2009

News: Property Appraiser Has Good News for Cedar Key
April 25th, 2009

News: Art Show Winners
April 22nd, 2009

News: Two Citizens Honored
April 22nd, 2009

News: One-way Traffic for Dock Street?
April 22nd, 2009

News: Solar Energy Blossoms in Cedar Key
April 10th, 2009

News: Traffic Consultant`s Plan Rejected
April 9th, 2009

More

Big Dock Update February 5

Big Dock Update February 5

Jim Hoy


Pilings in place as of January 31, 2008.

Construction of Cedar Key's new Big Dock is moving forward, with 25 percent of the pilings completed according to Fran Subjinski of Lucas Marine Construction. Delivery of concrete for the pilings via Dock Street has worked well Subjinski said. However, soon the newer pilings will be set farther off-shore and concrete deliveries will come to the end of A Street to be shuttled by barge to the construction site. Once one third of the pilings are in place construction of the dock's deck will begin.

Soil conditions (depth of bedrock) have been found to be quite variable. That has made it necessary to put pilings much deeper than had been expected. The problem arose despite two geotechnical surveys by Universal Engineering in 2007. The first piling in place was thirteen feet deeper than expected, at 73 feet. The remainder of the pilings are expected to be set at 48 to about 60 feet deep according to Mr. Philip Chansey of Mills Engineering, the Levy County engineering firm overseeing the project.

The County's contract with Lucas Marine Construction allows for a two week delay in completion of the work. That agreement reset the completion date as July 28, 2008.

Click for printer friendly version

Email this article to a friend

 

 

© 2013
Cedar Key News

cedarkeynews@gmail.com