Departments



Articles

Less

News: New Fire Chief for Cedar Key
June 12th, 2008

News: Plane Bound for Cedar Key Missing
June 7th, 2008

News: Big Dock Construction Update
June 5th, 2008

News: NOISE ORDINANCE MODIFIED AND PASSED
June 5th, 2008

News: Fire Chief McCain Resigns
June 4th, 2008

News: Interim Police Chief Named
June 4th, 2008

News: Fire Department Efforts Yield Lower Insurance Costs
June 1st, 2008

News: Horseshoe Crab Signs Inform Public
May 31st, 2008

News: Charges Pending in Fatality of Local Man
May 26th, 2008

News: Development Council Hears Overseas Investors Plan
May 24th, 2008

News: Terry "Red" Cole
May 24th, 2008

News: McCain Honored for 30 years of service
May 23rd, 2008

News: Police Department Update: May 21
May 21st, 2008

News: Proposed Noise Ordinance Tabled
May 21st, 2008

News: Over the Top!
May 20th, 2008

More

Big Dock Update February 5

Big Dock Update February 5

Jim Hoy


Pilings in place as of January 31, 2008.

Construction of Cedar Key's new Big Dock is moving forward, with 25 percent of the pilings completed according to Fran Subjinski of Lucas Marine Construction. Delivery of concrete for the pilings via Dock Street has worked well Subjinski said. However, soon the newer pilings will be set farther off-shore and concrete deliveries will come to the end of A Street to be shuttled by barge to the construction site. Once one third of the pilings are in place construction of the dock's deck will begin.

Soil conditions (depth of bedrock) have been found to be quite variable. That has made it necessary to put pilings much deeper than had been expected. The problem arose despite two geotechnical surveys by Universal Engineering in 2007. The first piling in place was thirteen feet deeper than expected, at 73 feet. The remainder of the pilings are expected to be set at 48 to about 60 feet deep according to Mr. Philip Chansey of Mills Engineering, the Levy County engineering firm overseeing the project.

The County's contract with Lucas Marine Construction allows for a two week delay in completion of the work. That agreement reset the completion date as July 28, 2008.

Click for printer friendly version