Departments



Articles

Less

News: "The Festival Times"
April 20th, 2007

News: Major Tax Rally in Tallahassee Tuesday
April 15th, 2007

News: The Natural Experience Gallery to Close
April 12th, 2007

News: Noise Ordinance Revised
April 4th, 2007

News: CRA: Where the Money Goes
April 2nd, 2007

News: Another Vessel on the Beach
April 1st, 2007

News: Proposed Merger of Water District with the City
March 8th, 2007

News: Dock Repair Bids Delayed
March 5th, 2007

News: Art Auctioned in Fund Raiser
March 4th, 2007

News: Island Room Benefit for Cedar Key School
February 23rd, 2007

News: Chamber of Commerce Told of Charter Government
February 22nd, 2007

News: Clammers and Scientists Meet
February 9th, 2007

News: Cemetery Fence on Table
February 8th, 2007

News: Festival Food Booths Under Control
February 8th, 2007

News: Rescue 75 Makes Debut
February 7th, 2007

More

Big Dock Update February 5

Big Dock Update February 5

Jim Hoy


Pilings in place as of January 31, 2008.

Construction of Cedar Key's new Big Dock is moving forward, with 25 percent of the pilings completed according to Fran Subjinski of Lucas Marine Construction. Delivery of concrete for the pilings via Dock Street has worked well Subjinski said. However, soon the newer pilings will be set farther off-shore and concrete deliveries will come to the end of A Street to be shuttled by barge to the construction site. Once one third of the pilings are in place construction of the dock's deck will begin.

Soil conditions (depth of bedrock) have been found to be quite variable. That has made it necessary to put pilings much deeper than had been expected. The problem arose despite two geotechnical surveys by Universal Engineering in 2007. The first piling in place was thirteen feet deeper than expected, at 73 feet. The remainder of the pilings are expected to be set at 48 to about 60 feet deep according to Mr. Philip Chansey of Mills Engineering, the Levy County engineering firm overseeing the project.

The County's contract with Lucas Marine Construction allows for a two week delay in completion of the work. That agreement reset the completion date as July 28, 2008.