Departments



Articles

Less

News: Arson Suspected in Dock Fire
September 27th, 2006

News: Bulkhead Requests Torpedoed
September 27th, 2006

News: $300,000 USDA Check for City
September 26th, 2006

News: L.P.A. Starts E.A.R.
September 22nd, 2006

News: Police Criticized before Commission
September 13th, 2006

News: Levy County Budget Now at $77,891,819
September 12th, 2006

News: 9/11 Memorial Service
September 11th, 2006

News: Firefighters Remember 9-11
September 10th, 2006

News: Cedar Key Tax Rate and Budget Set
September 8th, 2006

News: Tax Policies in Question
September 5th, 2006

News: Young Adult Books Are Available In Local Library
August 23rd, 2006

News: Smitty`s Bar-B-Que Opens
August 22nd, 2006

News: Brother Mike Serves First Baptist Church
August 19th, 2006

News: Fishing Bridge Declared Structurally Deficient
August 18th, 2006

News: City Commission OK`s Citizens` Petitions & Emergency Management Plan
August 17th, 2006

More

Big Dock Update February 5

Big Dock Update February 5

Jim Hoy


Pilings in place as of January 31, 2008.

Construction of Cedar Key's new Big Dock is moving forward, with 25 percent of the pilings completed according to Fran Subjinski of Lucas Marine Construction. Delivery of concrete for the pilings via Dock Street has worked well Subjinski said. However, soon the newer pilings will be set farther off-shore and concrete deliveries will come to the end of A Street to be shuttled by barge to the construction site. Once one third of the pilings are in place construction of the dock's deck will begin.

Soil conditions (depth of bedrock) have been found to be quite variable. That has made it necessary to put pilings much deeper than had been expected. The problem arose despite two geotechnical surveys by Universal Engineering in 2007. The first piling in place was thirteen feet deeper than expected, at 73 feet. The remainder of the pilings are expected to be set at 48 to about 60 feet deep according to Mr. Philip Chansey of Mills Engineering, the Levy County engineering firm overseeing the project.

The County's contract with Lucas Marine Construction allows for a two week delay in completion of the work. That agreement reset the completion date as July 28, 2008.