Departments



Articles

Less

News: Lions Club Building to Become City Community Center
August 17th, 2006

News: Technician/Code Enforcement Officer Begins Duties
August 10th, 2006

News: S.H.I.N.E. Offering Extra Help
August 6th, 2006

News: Student Authors Visit Commission Meeting
August 2nd, 2006

News: Commission Denys Bulkhead and Splits on Ordianace 405
August 2nd, 2006

News: Postmaster at Cedar Key
July 25th, 2006

News: Building Department Fees Approved
July 19th, 2006

News: Paving Project Completed
July 12th, 2006

News: Clamerica is Big Success
July 11th, 2006

News: Clamerica `06 Clicks
July 4th, 2006

News: Bachelor Auction Nets Rewards for Local Youth
July 3rd, 2006

News: Muir Inspired Hikers
June 25th, 2006

News: Bachelor Auction Benefits School and Library
June 23rd, 2006

News: Bulkhead Requests 1-1-1
June 21st, 2006

News: CK Commission Retreat June 15
June 19th, 2006

More

Big Dock Update February 5

Big Dock Update February 5

Jim Hoy


Pilings in place as of January 31, 2008.

Construction of Cedar Key's new Big Dock is moving forward, with 25 percent of the pilings completed according to Fran Subjinski of Lucas Marine Construction. Delivery of concrete for the pilings via Dock Street has worked well Subjinski said. However, soon the newer pilings will be set farther off-shore and concrete deliveries will come to the end of A Street to be shuttled by barge to the construction site. Once one third of the pilings are in place construction of the dock's deck will begin.

Soil conditions (depth of bedrock) have been found to be quite variable. That has made it necessary to put pilings much deeper than had been expected. The problem arose despite two geotechnical surveys by Universal Engineering in 2007. The first piling in place was thirteen feet deeper than expected, at 73 feet. The remainder of the pilings are expected to be set at 48 to about 60 feet deep according to Mr. Philip Chansey of Mills Engineering, the Levy County engineering firm overseeing the project.

The County's contract with Lucas Marine Construction allows for a two week delay in completion of the work. That agreement reset the completion date as July 28, 2008.

Click for printer friendly version