Departments



Articles

Less

News: Photo Show Winners
April 4th, 2006

News: C K Men Winners in Tournament
April 4th, 2006

News: Air Boat regatta Under New Rules
April 2nd, 2006

News: Business of the Year Award
March 31st, 2006

News: Fine Arts Show Rebirth
March 30th, 2006

News: Suwannee Triangle Gallery Farewell
March 29th, 2006

News: Lions Host District Governor
March 28th, 2006

News: #4 Bridge Fishing Pier to Open to Public
March 28th, 2006

News: Boats of Wood, Men of Steel
March 24th, 2006

News: Second Annual Lions Club Health Fair
March 17th, 2006

News: Judge Takes Pipeline Process from FL DEP
March 15th, 2006

News: Water District Solves Trihalomethane Problem
March 14th, 2006

News: Pipeline Project Not Well Received
March 11th, 2006

News: Development Issues Dominate Commission Meeting
March 8th, 2006

News: Irish Delegation Meets City Commissioners
March 6th, 2006

More

Big Dock Update February 5

Big Dock Update February 5

Jim Hoy


Pilings in place as of January 31, 2008.

Construction of Cedar Key's new Big Dock is moving forward, with 25 percent of the pilings completed according to Fran Subjinski of Lucas Marine Construction. Delivery of concrete for the pilings via Dock Street has worked well Subjinski said. However, soon the newer pilings will be set farther off-shore and concrete deliveries will come to the end of A Street to be shuttled by barge to the construction site. Once one third of the pilings are in place construction of the dock's deck will begin.

Soil conditions (depth of bedrock) have been found to be quite variable. That has made it necessary to put pilings much deeper than had been expected. The problem arose despite two geotechnical surveys by Universal Engineering in 2007. The first piling in place was thirteen feet deeper than expected, at 73 feet. The remainder of the pilings are expected to be set at 48 to about 60 feet deep according to Mr. Philip Chansey of Mills Engineering, the Levy County engineering firm overseeing the project.

The County's contract with Lucas Marine Construction allows for a two week delay in completion of the work. That agreement reset the completion date as July 28, 2008.