Departments



Articles

Less

News: Sturmer honored by CKAA
June 19th, 2006

News: Media Floods Cedar Key
June 13th, 2006

News: Kayak Race Fourth of July
June 8th, 2006

News: Bulkhead Questioned by Commissioners
June 7th, 2006

News: Class of 2006 Graduates May 20
May 23rd, 2006

News: Building Dept. Reorganization Soon
May 17th, 2006

News: Seniors Revisit Kindergarten Quilt
May 15th, 2006

News: A Loan TO the Library
May 9th, 2006

News: Local Educator Honored at State Meet
May 5th, 2006

News: Two New Faces on the Water Board
May 2nd, 2006

News: Wind Delays Dock Project
April 27th, 2006

News: Land Use Issues Dominate Commission Meeting
April 21st, 2006

News: Cedar Key Arts Show Has Many Winners
April 9th, 2006

News: Cedar Key Arts Show Opens April 8
April 8th, 2006

News: Park Plans Pester Commissioners
April 5th, 2006

More

Big Dock Update February 5

Big Dock Update February 5

Jim Hoy


Pilings in place as of January 31, 2008.

Construction of Cedar Key's new Big Dock is moving forward, with 25 percent of the pilings completed according to Fran Subjinski of Lucas Marine Construction. Delivery of concrete for the pilings via Dock Street has worked well Subjinski said. However, soon the newer pilings will be set farther off-shore and concrete deliveries will come to the end of A Street to be shuttled by barge to the construction site. Once one third of the pilings are in place construction of the dock's deck will begin.

Soil conditions (depth of bedrock) have been found to be quite variable. That has made it necessary to put pilings much deeper than had been expected. The problem arose despite two geotechnical surveys by Universal Engineering in 2007. The first piling in place was thirteen feet deeper than expected, at 73 feet. The remainder of the pilings are expected to be set at 48 to about 60 feet deep according to Mr. Philip Chansey of Mills Engineering, the Levy County engineering firm overseeing the project.

The County's contract with Lucas Marine Construction allows for a two week delay in completion of the work. That agreement reset the completion date as July 28, 2008.