Departments



Articles

Less

News: Sign Ordinance Revision Planned
December 16th, 2009

News: Garbage Contract Up for Bids?
December 16th, 2009

News: Whooping Cranes Half Way to Florida
December 7th, 2009

News: Former County Commissioners Convicted
December 5th, 2009

News: Duke Indicted on First Degree Murder
November 22nd, 2009

News: Grand Opening at Historical Society
November 16th, 2009

News: Book Launched in Cedar Key
November 15th, 2009

News: CRA Near Start of Major Project
November 13th, 2009

News: $2 Million Bond Set on Murder Suspect
November 6th, 2009

News: Update With Funeral Arrangements: Cedar Key Woman Dead, Husband In Custody
November 5th, 2009

News: Illegal Dumping Disrupts Sewage Treatment
November 5th, 2009

News: Commission Eyes Sign Ordinance, Solid Waste and Cell Tower
November 4th, 2009

News: FATAL BEAR FIGHT
October 23rd, 2009

News: Public Outcry Over Restaurant Name
October 21st, 2009

News: Seafood Festival Parade Winners
October 19th, 2009

More

Water Pipeline to Airport Area

Water Pipeline to Airport Area

Jim Hoy

Representatives of the Cedar Key Water and Sewer District, City Commission, Community Redevelopment Agency (CRA) and Levy County met March 19 to plan for better water service to the Airport area. A proposed eight inch diameter 2000 foot long pipeline under Goose Cove is expected to provide adequate water and volume to fight fires, in contrast to the current supply via a four inch pipe.

Most homes in the airport area are in Levy County but not incorporated in Cedar Key. The City Commission, which also constitutes the CRA, plans to fund the pipeline which is currently estimated to cost $184,000. Levy County residents will benefit from the project as well as those property owners who have annexed into Cedar Key, therefore a promise of county construction equipment for the project.

The pipeline under Goose Cove will be installed by directional boring of a 2000 foot long hole according to Jack Hotaling who is in charge of Water District engineering. This project has been described as "historic" by a Water Board member in that the four government entities are working in close cooperation. Once appropriate permits have been granted the work will take approximately three months.