Departments



Articles

Less

News: Whooping Cranes Near
December 11th, 2005

News: April Arts Show Rich in Awards
December 9th, 2005

News: Rock the Boat Art Show
December 9th, 2005

News: Conservation Zone Debate Putover til Jan. 17
December 7th, 2005

News: Who Wants to Do Raku?
December 6th, 2005

News: Whooping Crane Update
December 2nd, 2005

News: LPA Acts on Docks andParking
November 30th, 2005

News: Conservation Zone Debate -- Again
November 16th, 2005

News: Dock Fire at Natures Landing
November 15th, 2005

News: Red Tide Closes Shellfish Harvest
November 4th, 2005

News: Commission Does Housekeeping
November 2nd, 2005

News: Class of 1965 Holds Reunion
November 1st, 2005

News: Buckeye Technologies Defends Waste Water Pipeline
October 28th, 2005

News: Kids Bumped from Golf Carts
October 19th, 2005

News: Net Ban Revisited
October 14th, 2005

More

Big Dock Reconstruction Begins / Updated Nov. 14

Big Dock Reconstruction Begins / Updated Nov. 14

Jim Hoy


The barge that will be used during the reconstructionof the Cedar Key dock.

The dramatic arrival of two tug boats and an eighty-five foot barge at the Cedar Key "Big Dock" on November 12 announced the start of rebuilding the storm-damaged dock. According to Levy County Coordinator Fred Moody, a contract for the construction project was to be signed November 13. After years and months of delay, a commitment by Levy County to provide $643,000 in supplementary funds in addition to $3.1 million in Federal Emergency Management Agency funds got the project underway. Mr. Moody told Cedar Key News that there is a possibility that FEMA will reimburse the County with cost over-run funds at the end of the project.

Update: On November 14 Lucas Marine Construction hosted an informational meeting regarding the reconstruction of the Cedar Key "Big Dock." Actual construction will begin on November 19, with a contract to finish work within 240 days. If that dadline is met the new dock will be finished before onset of the 2008 hurricane season.

Frank Subjinski, a Lucas Marine Vice President, said that the dock will have a concrete pre-stressed deck with a concrete overlay. There will be a thirty foot long aluminum ramp from Dock Street to the higher level dock. The ramp will be removable prior to a storm. Shafts for the concrete pilings will be drilled, an alternative to use of a pile driver.

The contract is for $3,596,357.