Departments



Articles

Less

News: Maria Thompson, in Long Term Care Near Fanning Springs, Welcomes Visits
April 28th, 2013

News: World Travelers - From Antarctica to Cedar Key
April 26th, 2013

News: FARAWAY INN AWARDED TRIPADVISOR GREENLEADERS™ STATUS
April 26th, 2013

News: Pirates invade Cedar Key to Help Local Charities
April 22nd, 2013

News: EIGHT GOLD SHOVELS BREAK GROUND IN CEDAR KEY
April 16th, 2013

News: Prepare to be boarded !!!
April 12th, 2013

News: Arbor Day 2013 - Cedar Key, Florida
April 10th, 2013

News: News from the Pirates
April 3rd, 2013

News: Hummingbirds
April 1st, 2013

News: Faraway Inn Begins Phones for Earth Day Campaign
March 29th, 2013

News: Book Bunch News
March 29th, 2013

News: MAYOR GENE HODGES UPDATE
March 26th, 2013

News: Demystifying Shell Mound 2013
March 26th, 2013

News: Musings on Community Theatre
March 23rd, 2013

News: WORKFORCE CONNECTION VISITS CEDAR KEY
March 21st, 2013

More

Water Pipeline to Airport Area

Water Pipeline to Airport Area

Jim Hoy

Representatives of the Cedar Key Water and Sewer District, City Commission, Community Redevelopment Agency (CRA) and Levy County met March 19 to plan for better water service to the Airport area. A proposed eight inch diameter 2000 foot long pipeline under Goose Cove is expected to provide adequate water and volume to fight fires, in contrast to the current supply via a four inch pipe.

Most homes in the airport area are in Levy County but not incorporated in Cedar Key. The City Commission, which also constitutes the CRA, plans to fund the pipeline which is currently estimated to cost $184,000. Levy County residents will benefit from the project as well as those property owners who have annexed into Cedar Key, therefore a promise of county construction equipment for the project.

The pipeline under Goose Cove will be installed by directional boring of a 2000 foot long hole according to Jack Hotaling who is in charge of Water District engineering. This project has been described as "historic" by a Water Board member in that the four government entities are working in close cooperation. Once appropriate permits have been granted the work will take approximately three months.