Departments



Articles

Less

News: Former Mayor J.Q. Hodges Victimized
August 19th, 2005

News: Commission Rejects Three Changes in Zoning
August 18th, 2005

News: Local Artist to be Featured by National Art Publishing Firm
August 16th, 2005

News: Cedar Key Arts Show Renewal
August 9th, 2005

News: Police Beat/ August 4
August 4th, 2005

News: Cemetery Point Park Planning
August 3rd, 2005

News: Highway 24 Resurfacing Scheduled
July 29th, 2005

News: Police Beat
July 27th, 2005

News: Scholarship to Cedar Key Grad
July 24th, 2005

News: Sheriff`s Office Honors Retiring Volunteer Coordinator
July 21st, 2005

News: Conservation Zone Map Reviewed
July 20th, 2005

News: Missing Beer Evidence of Felony
July 19th, 2005

News: Health Department Visits Cedar Key
July 12th, 2005

News: Water Board to Try Ionic Ultra Filtration
July 12th, 2005

News: Revenue Sharing
July 8th, 2005

More

Water Pipeline to Airport Area

Water Pipeline to Airport Area

Jim Hoy

Representatives of the Cedar Key Water and Sewer District, City Commission, Community Redevelopment Agency (CRA) and Levy County met March 19 to plan for better water service to the Airport area. A proposed eight inch diameter 2000 foot long pipeline under Goose Cove is expected to provide adequate water and volume to fight fires, in contrast to the current supply via a four inch pipe.

Most homes in the airport area are in Levy County but not incorporated in Cedar Key. The City Commission, which also constitutes the CRA, plans to fund the pipeline which is currently estimated to cost $184,000. Levy County residents will benefit from the project as well as those property owners who have annexed into Cedar Key, therefore a promise of county construction equipment for the project.

The pipeline under Goose Cove will be installed by directional boring of a 2000 foot long hole according to Jack Hotaling who is in charge of Water District engineering. This project has been described as "historic" by a Water Board member in that the four government entities are working in close cooperation. Once appropriate permits have been granted the work will take approximately three months.