Departments



Articles

Less

News: Cedar Key Commission Meeting Highlights
April 7th, 2005

News: Concensus Report from the 2004 Charrette
March 31st, 2005

News: Fire Protection Discussed
March 26th, 2005

News: Hotly Contested Elections in May
March 26th, 2005

News: City Tranfers Dock Leases
March 17th, 2005

News: Housing Rumors Dispelled
March 6th, 2005

News: Trojan Horse Visits Cedar Key
March 6th, 2005

News: Health Needs Survey Reported
March 4th, 2005

News: Proposal to Buy Docks
February 24th, 2005

News: Plane Crashes in Cedar Key Fog (updated photos)
February 22nd, 2005

News: Accord Insurance Open for Business
February 16th, 2005

News: Purchase of the Big Dock?
February 16th, 2005

News: Cedar Key Commission Grapples with Fire Protection
February 6th, 2005

News: Green Replat Request Denied
January 19th, 2005

News: Gulf Trail Sunk
January 5th, 2005

More

Big Dock Update February 5

Big Dock Update February 5

Jim Hoy


Pilings in place as of January 31, 2008.

Construction of Cedar Key's new Big Dock is moving forward, with 25 percent of the pilings completed according to Fran Subjinski of Lucas Marine Construction. Delivery of concrete for the pilings via Dock Street has worked well Subjinski said. However, soon the newer pilings will be set farther off-shore and concrete deliveries will come to the end of A Street to be shuttled by barge to the construction site. Once one third of the pilings are in place construction of the dock's deck will begin.

Soil conditions (depth of bedrock) have been found to be quite variable. That has made it necessary to put pilings much deeper than had been expected. The problem arose despite two geotechnical surveys by Universal Engineering in 2007. The first piling in place was thirteen feet deeper than expected, at 73 feet. The remainder of the pilings are expected to be set at 48 to about 60 feet deep according to Mr. Philip Chansey of Mills Engineering, the Levy County engineering firm overseeing the project.

The County's contract with Lucas Marine Construction allows for a two week delay in completion of the work. That agreement reset the completion date as July 28, 2008.