Departments



Articles

Less

News: Clamerica Thrives in `05
July 8th, 2005

News: Fleeing, but Not Eluding
July 6th, 2005

News: Paving Issues Aired at Commission
July 6th, 2005

News: LPA Nixes Map Changes
July 1st, 2005

News: State Water Reps Test Local Supply
July 1st, 2005

News: Arts Festival Accounting Released
June 26th, 2005

News: Child Welfare Case Leads to Drug Arrests
June 25th, 2005

News: Building Official Resigns
June 23rd, 2005

News: Spate of Cedar Key Burglaries
June 16th, 2005

News: Superstructure Arises
June 9th, 2005

News: Anchor Hole Parking to Move
June 8th, 2005

News: CRA Director Search Narrows
June 6th, 2005

News: Police Chase to Otter Creek
May 31st, 2005

News: Cedar Key War Memorial
May 30th, 2005

News: Dock Grant on Governor`s Desk
May 26th, 2005

More

Big Dock Update February 5

Big Dock Update February 5

Jim Hoy


Pilings in place as of January 31, 2008.

Construction of Cedar Key's new Big Dock is moving forward, with 25 percent of the pilings completed according to Fran Subjinski of Lucas Marine Construction. Delivery of concrete for the pilings via Dock Street has worked well Subjinski said. However, soon the newer pilings will be set farther off-shore and concrete deliveries will come to the end of A Street to be shuttled by barge to the construction site. Once one third of the pilings are in place construction of the dock's deck will begin.

Soil conditions (depth of bedrock) have been found to be quite variable. That has made it necessary to put pilings much deeper than had been expected. The problem arose despite two geotechnical surveys by Universal Engineering in 2007. The first piling in place was thirteen feet deeper than expected, at 73 feet. The remainder of the pilings are expected to be set at 48 to about 60 feet deep according to Mr. Philip Chansey of Mills Engineering, the Levy County engineering firm overseeing the project.

The County's contract with Lucas Marine Construction allows for a two week delay in completion of the work. That agreement reset the completion date as July 28, 2008.